DAR-MinSAAD

Construction of Pinamangguan Communal Irrigation Project (CIP)

Aug. 7, 2018Start

Jun. 3, 2019End

₱15744409.07

80.00 qty

Turned-Over

Sub-Project Details:

Contact regarding the Sub-Project (SP)

Area: Kadingilan, Bukidnon, Region X

Sub-Project Funds:

Approved:

LP Cost: ₱

15758039.00

GOP Cost: ₱

2117970.20

MinSAAD Cost: ₱

17876009.20

Agency Cost: ₱

0

Total Project Cost: ₱

17876009.20

Cash Released to Agency:

LP Cost: ₱

17483915.77

GOP Cost: ₱

2322300.34

MinSAAD Cost: ₱

19806216.11

CAW 1 / CAW 2:

LP Cost: ₱

15282716.00

GOP Cost: ₱

2322300.00

MinSAAD Cost: ₱

17605016.00

Agency Cost: ₱

0

Total Project Cost: ₱

17605016.00

Contracted:

Project Cost: ₱

15744409.07

Implementation Date:

Target:

Actual:

Cash Released, CAWs & Contracted:

Implementation Unit:

Sub-Project Pictures

Related Sub-Projects (SPs)

₱13992940.21

Taytay Unggoy CIP is one of the three systems in Barangay Pinamangguan which has a total area of 259 ha. The potential area of the Taytay Unggoy CIP is 62 hectares. At present only 3 ha. are planted during rainy

Kadingilan, Bukidnon, Region X

₱10371698.22

Talasan CIS is one ot the three systems in Barangay Pinamangguan which has a total area of 259 ha. The potential area of the Talasan CIS is 123 ha., at present only 23 ha. were irrigated. The major source of

Kadingilan, Bukidnon, Region X